The Low Carbon Partnership

Lewisham Hospital

"From our experience at Lewisham Hospital, we have found Dulas to be one of our better sub-contractors, with a genuinely co-operative approach, proactive design, delivered with reliable and safety-conscious on-site performance.”

Mowlem

Implementation & use

Management Mowlem
Installation Dulas Ltd

Technical specification

Technology 72 Kyocera KC190
Inverter 3x Fronius IG40
Mounting system Schletter flat roof mounting structure

 


The story

To install 13.68kWp Photovoltaic system on the new extension at Lewisham Hospital, London SE14. To increase staff and patient awareness of renewable solutions.

The system was to a very tight schedule in order to fit in with access scaffolding and temporary hoists installed for the new-build hospital. Dulas worked with the designers from Mowlem and found a robust and durable solution to fit in with the S shaped Kingspan KS1000 RW roof, supported on steel purlins.


Social Housing Schools & Colleges Council Buildings Health Care Community Groups All Projects Apply Now News